Clients often assume a redesign is the quick option: the content exists, the domain exists, the structure exists – just make it look better. Others assume a new build is simpler because there is no legacy to deal with. Our records tell a more nuanced story.
We split our 110 WordPress projects into redesigns (the project was explicitly a redesign, relaunch or rebuild of an existing site) and new builds.
The numbers side by side
| Redesign | New build | |
|---|---|---|
| Projects | 17 | 93 |
| Median delivery time | 36 days | 31 days |
| Median time to go-live (where tracked) | 21 days | 30 days |
| Median hours logged | 14.5 | 15.4 |
| Median revision rounds | 3 | 2 |
The honest summary: neither type is dramatically faster. Redesigns needed a similar amount of work, reached go-live sooner where we tracked it, but tended to have one more revision round. The redesign sample is smaller, so we read these as tendencies rather than rules.
Why redesigns get more revision rounds
A redesign has an invisible competitor: the old website. Clients compare every section to what they had before, and stakeholders who never cared about the old site suddenly have strong opinions about the new one. In the feedback documents of our redesign projects, three topics came up repeatedly:
- "Keep what worked." A section, a phrase or a feature from the old site that nobody mentioned in the brief turns out to be important.
- Content that was never updated. Old service descriptions, outdated team members, prices from years ago. A redesign exposes all of it.
- Brand consistency. If the corporate identity stays, fonts, colours and logo use have to match exactly, and small deviations get noticed.
Why new builds take longer to start
New builds have the opposite problem: nothing exists yet. The first draft depends on decisions that a redesign inherits – the page structure, the services, the tone, the logo. New businesses often launch the website alongside their brand, which means the website becomes the place where the brand gets decided. Fonts and colours come up in feedback because they are being chosen in real time.
New builds also have more "first time" tasks at launch: registering or connecting a domain, setting up business email, creating a Google Business Profile, writing legal pages from scratch.
Redesign-specific risks we plan for
Losing search visibility
A redesign on an existing domain carries SEO risk. If page URLs change and nobody sets up redirects, old links and rankings break. We map the old URLs before launch and redirect every relevant one. We also check that the new site is not accidentally set to "noindex" – a mistake we have found on sites built elsewhere.
Legacy plugins and hosting
Older WordPress sites often come with years of plugins, some unmaintained. In one redesign, a single outdated plugin caused a server error on the whole site; we deactivated it and replaced its function. Sometimes the cleaner option is to rebuild on a fresh installation and migrate only the content.
Access to the old setup
For redesigns, we need logins to the existing site, hosting and domain. These are often held by a former agency or an employee who has left. Start looking for them on day one.
New-build-specific risks we plan for
- Content from scratch. Every text has to be written. We often draft the texts and the client approves them.
- Photos. There may be no photos of the team or premises yet. Decide early whether to launch with licensed stock images.
- Legal pages. Imprint and privacy policy need company details that may not be final for a new business.
How we run the first week of each type
For a redesign, the first week is an inventory. We crawl the existing site, list every page and its URL, note which pages bring traffic and which forms or integrations exist. Then we agree with the client which pages survive, which merge and which disappear. That list becomes both the new sitemap and the redirect plan.
For a new build, the first week is about decisions. We confirm the services, the target audience, the main call to action and the brand basics. If the logo or colours are not final, we say so openly and agree whether the website waits or moves ahead with a provisional design.
In both cases, the kickoff call ends with a list of what we need from the client and by when. It is the same principle our fastest projects share: fewer open questions at the start means fewer surprises in the revision rounds.
Which one should you choose?
If your current site has a solid structure, good rankings and mostly up-to-date content, a redesign that keeps the URL structure is usually the right call. If the structure no longer fits your services, the content is largely outdated, or the old technology is a burden, treat it as a new build – even if you keep the domain.
The question that decides it for us: how much of the existing content would survive unchanged? If the answer is "not much", calling it a redesign only sets the wrong expectations.
FAQ
Is a redesign cheaper than a new website?
In our data, the logged hours were similar. A redesign saves time on structure and content, but spends it on matching the old site's details and cleaning up legacy issues.
Will a redesign hurt my Google rankings?
It can if URLs change without redirects or if the new site is set to noindex. With a proper redirect plan and a launch check, rankings are usually stable or improve.
Can we keep our old texts?
Yes, and it speeds things up – if the texts are still accurate. We usually recommend at least updating services, team and contact details during a redesign.
Will I need changes after my website launches?
Probably. 34% of our WordPress projects with a go-live had change requests afterwards, the first one a median of 12 days after launch. Plan a small budget or a support plan for this phase.
Do GDPR and cookie topics really come up in most projects?
Often. Cookie consent, legal pages or embedded third-party content came up in 35% of our WordPress projects and 62% of our Shopify projects. We set up the consent tool; the legal texts come from the client or their legal adviser.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.