If there is one lever clients control that changes a website timeline more than any other, it is feedback. We counted revision rounds in our finished website and landing page builds and compared them with delivery time.
| Revision rounds | Builds | Median delivery time |
|---|---|---|
| 0 | 26 | 8.5 days |
| 1 | 32 | 15.5 days |
| 2 | 36 | 22 days |
| 3 | 23 | 64 days |
| 4 or more | 46 | 58.5 days |
The jump between two and three rounds is striking. Up to two rounds, projects move steadily. From the third round on, the median delivery time roughly triples. It is rarely the building that takes long: each round adds days of waiting for the next batch of feedback.
In our WordPress projects the median was 2 rounds. 16 projects had no revision round at all, while 9 went through six or more.
Why rounds multiply
From reading the feedback in our projects, a few patterns explain most extra rounds:
- Feedback arrives in pieces. One email today, a WhatsApp screenshot tomorrow, a colleague's comments next week. Each piece triggers a partial update, and the round never closes.
- Several people comment independently. The owner likes the headline, the sales manager wants it changed, the partner prefers the original. We implement one opinion, then the next.
- Content changes during review. New texts replace approved ones, which changes layouts that were already fine.
- Mobile is checked last. Mobile issues discovered in round three sometimes require restructuring sections approved on desktop.
- New ideas join the list. "While you're at it, could we add…" Scope additions are welcome but belong in a separate list.
A feedback method that works
1. Collect internally first
Share the staging link with everyone who needs to have a say. Give them a deadline. Collect all comments in one place and resolve contradictions before sending them to us.
2. One document per round
Feedback arrives in many formats – Word files, PDFs, annotated screenshots, voice-note style lists, colour-coded documents. All work, as long as there is one consolidated document per round. A simple structure:
| Page | Section | Device | What to change | Priority |
|---|---|---|---|---|
| Home | Hero | Phone | Headline too large, wraps into four lines | Must |
| Services | Card 3 | All | Replace text with attached version | Must |
| About | Team | All | Photo of new colleague to add | Nice to have |
3. Be specific
"Make it more modern" is hard to implement. "Use more white space between sections and a lighter grey background" is easy. If you do not know how to describe it, point to an example on another site.
4. Screenshots help
An annotated screenshot removes all doubt about which element you mean.
5. Check on your phone first
Most visitors will. Mobile issues found in round one are quick fixes.
6. Separate corrections from new ideas
Corrections go into the round. New pages, features or sections go on a separate list, which we can quote or plan for after launch.
What good feedback looks like
The fastest projects in our data did not have perfect first drafts. They had clients who reviewed within a few days, sent one clear list, and trusted the team with details. Our fastest quarter of WordPress projects had a median of 0.5 revision rounds and waited on the client for 1.5 days; the slowest quarter had 3.5 rounds and 81 days of client waiting.
How we handle feedback on our side
Each round becomes its own task in our project system, with the client's document attached. We implement every point, mark each as done or add a question, and send the updated staging link with a short summary. If something was not implemented, we explain why – for example, a technical limitation or a conflict with another request.
Paid revisions are rare: only 6% of WordPress projects included one. Most projects stay within the rounds included in the package when feedback is consolidated.
Who should give feedback?
The ideal is one decision maker with the authority to approve. Others can contribute, but their comments go through that person. When several people send feedback directly, rounds multiply: each round answers one voice and opens new questions for the others. Naming the approver at kickoff is one of the simplest ways to shorten a project.
A realistic target
For a typical company website, aim for two rounds: one for structure and design, one for details. That is where our data shows delivery stays predictable.
FAQ
How many revision rounds are included?
That depends on the package, but our process is designed around two to three consolidated rounds for a standard website.
Can I send feedback by WhatsApp or voice message?
You can, and many clients do. But please collect everything for one round before sending, so we can implement it in one go.
What if I change my mind after approving something?
It happens. Small changes are fine; larger direction changes after approval may count as an extra round or new work, which we will tell you upfront.
Why does one decision maker matter so much?
Because feedback from several people without a final say turns into extra revision rounds. In our experience a single person who collects feedback and approves is the biggest time-saver on the client side.
How often do maintained websites need work?
Across our 18 maintenance retainers, clients sent a median of 4.3 requests per month, ranging from 1.2 to 14.7.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.