A brief is more than a description of what you want. It sets up how the project will run: who decides, what content exists, what access we get and what "done" means. We looked at our own records to see what separates fast projects from slow ones, and the brief – plus the decisions around it – explains most of the difference.
What our data shows
We split our 110 WordPress website projects into quartiles by duration and compared the fastest 30 with the slowest 28.
| Fastest quartile | Slowest quartile | |
|---|---|---|
| Median duration | 11 days | 134.5 days |
| Median days waiting on the client | 1.5 | 81 |
| Median days of team work | 8 | 26 |
| Median revision rounds | 0.5 | 3.5 |
| Missing content came up | 7% | 29% |
| Scope changes came up | 7% | 25% |
The team work differed by weeks. The waiting differed by months. For landing pages, the pattern is the same: the fastest quartile took a median of 7 days, the slowest 33 days, with 1 versus 22 days of client waiting.
Interestingly, sending reference websites and a content document was common in both groups. Having those is a good start – but what makes the difference is whether the content is complete, the scope stays stable and feedback comes back quickly.
What a good brief contains
1. Goal and audience
- What should the website achieve? Enquiries, bookings, sales, recruiting, credibility?
- Who are the main visitors, and what do they need to find?
- What is the one action you want visitors to take?
2. Scope
- List of pages, or a sitemap draft
- Features: forms, booking, shop, multilingual, member area, integrations
- What is explicitly not included in this phase
Writing down what is out of scope is as useful as what is in. Scope changes appeared in 25% of our slowest projects versus 7% of the fastest.
3. Content status
- Which texts exist, which need writing, and who writes them
- Images: available, to be photographed, or stock
- Legal pages: imprint, privacy policy
Be honest about content. "The texts are almost ready" is the most common reason for a timeline to slip.
4. Brand
- Logo files, colours, fonts
- Examples of websites you like, and what exactly you like about them
Fonts, colours and design details came up in 52% of our WordPress projects. Clear brand inputs reduce that feedback.
5. Access
- Domain registrar, DNS, hosting, existing website admin
- Google Analytics, Search Console, tag manager
- Any third-party tools to connect
Hosting and DNS topics came up in 25% of our WordPress projects. Having the access sorted before the go-live week prevents last-minute delays.
6. Decision maker and feedback process
- One person who collects feedback and approves
- Who else needs to see drafts, and when
- How quickly feedback can be given
This is the least visible part of a brief and the most important. Our slowest projects were not slow because of difficult design; they were slow because approvals took weeks.
7. Deadline and why
A deadline with a reason (a trade fair, a campaign launch, a new product) helps everyone plan. Tell us about fixed dates at the start, not two weeks before.
What we do with the brief
After receiving a brief, we clarify open points, confirm the scope in writing and plan the phases. Our first drafts for WordPress websites came a median of 8 days after the start. From there, the pace depends mostly on content and feedback.
Brief checklist
- [ ] Goal, audience and main call to action
- [ ] Page list and features, with what is out of scope
- [ ] Content status: texts, images, legal pages
- [ ] Brand assets and reference sites
- [ ] Access to domain, hosting and tools
- [ ] One named decision maker
- [ ] Deadline and the reason for it
Common mistakes in briefs
- Describing the design instead of the goal. "We want a modern website" says little. "We want more enquiries from companies in our region" gives direction.
- Listing every possible feature. Start with what is needed for launch and plan the rest as a second phase.
- Leaving out the internal process. If the board must approve the design, say so at the start and plan for it.
- No owner for content. If nobody is responsible for texts, they will not appear on time.
You do not need a perfect document
A brief does not have to be long or formal. A short call where we go through these points together often works better than a written document. What matters is that the answers exist before the design starts.
FAQ
Do you have a brief template?
Yes. We share a short questionnaire at the start of each project and can go through it with you on a call.
What if we do not know all the answers yet?
That is normal. We help clarify goals and scope in a first workshop, and mark open points so they do not block the start.
Does a longer brief mean a faster project?
Not necessarily. Completeness of content, a stable scope and quick feedback matter more than the length of the brief.
What do the fastest website projects do differently?
Our fastest quarter of WordPress projects took a median of 11 days, the slowest 134.5 days. The team work differed far less than the waiting: 1.5 versus 81 days spent waiting on the client.
What delays website projects the most?
Waiting. Across our website and shop builds, 61% of the time between the first draft and go-live was spent waiting on the client – for content, feedback, approvals or access – not on design or development.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.