Clients often ask whether they should book a project or a retainer. The answer depends on the kind of work. We run both models: fixed-scope builds for websites, shops and landing pages, and monthly retainers for maintenance, marketing support and ongoing development. Our records show clear patterns for where each model works.
Two types of work
Project work has a defined result and an end: a new website, a landing page, a shop, a migration. The scope can be described before starting.
Ongoing work has no natural end: updates, fixes, content changes, campaign assets, integrations, small improvements. The volume changes from month to month.
The mistake we see most is using one model for both types.
What our project data shows
Across our 110 WordPress projects, the median project logged 15.2 of work, with the middle half between 9.3 and 32.1. Delivery took a median of 31.5 days. That spread is manageable when the scope is defined – which is exactly what a fixed-scope project needs.
What changes the effort within a project:
- Revision rounds: builds with two rounds took a median of 22 days, with four or more 58.5 days
- Scope changes, which came up in 15% of WordPress projects
- Content we were asked to write during the project
A good fixed-scope offer defines how many revision rounds are included and what counts as a change request.
What our retainer data shows
We analysed 209 requests across 18 maintenance and support retainers:
- A median of 4.3 requests per month per client, ranging from 1.2 to 14.7
- A median of 1.2 per request
- Bug fixes made up 21% of requests, marketing assets 16%, content and design changes 13%, integrations 11%
The requests are small but constant, and they vary widely between clients. Quoting each one separately would create more admin than work. That is why a retainer fits this type of work better.
Post-launch work: where the models meet
Websites do not stop needing work at launch. 34% of our WordPress projects with a go-live had change requests afterwards, the first one a median of 12 days after launch.
This is the natural handover point: the fixed-scope project delivers the website, and a retainer (or an agreed hourly model) covers everything that comes after.
When a fixed-scope project fits
- The result can be described clearly: pages, features, integrations
- Content is mostly available or its creation is part of the scope
- There is one decision maker
- The client wants budget certainty
When a retainer fits
- Regular small requests: updates, fixes, content, campaign assets
- Ongoing marketing: SEO, ads management, email campaigns
- Continuous development on a platform
- The client wants a team available without negotiating every task
Comparison
| Fixed-scope project | Retainer | |
|---|---|---|
| Best for | Defined results with an end | Ongoing, variable work |
| Budget | Known upfront | Predictable monthly |
| Changes | Handled as change requests | Absorbed into the monthly hours |
| Risk of scope discussions | Higher if scope is vague | Lower |
| Admin | One offer | One monthly report |
| Priority | Planned timeline | Ongoing availability |
Hybrid models
Many of our client relationships combine both: a fixed-scope build, then a retainer for maintenance and improvements. Larger features during a retainer can still be scoped as small projects. This keeps budgets clear for big items and flexible for small ones.
How we make retainers transparent
Retainers only work with transparency. We log time on each request, so clients can see what the hours were used for. The monthly report shows the requests, the time spent and anything we noticed proactively, such as updates due or security issues. This also shows whether the retainer size matches reality, and we adjust it if it does not.
Signs you are in the wrong model
- A fixed-scope project with constant new requests: the project never ends and both sides get frustrated. Split out the extras into a retainer or phase two.
- A retainer with little or no usage: the hours are paid but not used. Reduce it or switch to on-demand support.
- A retainer used for a large build: the build competes with urgent small tasks. Scope the build separately.
How to choose
Ask two questions. Can the result be described fully today? Will there be work after it is done? If yes to the first, start with a project. If yes to the second, plan a retainer for afterwards. Most websites need both.
FAQ
Do unused retainer hours roll over?
It depends on the agreement. We discuss this at the start so it matches how your requests usually come in.
Can a small website be done without a retainer?
Yes. Some clients handle small changes themselves or book support on demand. The key is knowing who does updates and backups.
How do you handle changes in a fixed-scope project?
We agree on included revision rounds at the start. Anything beyond the agreed scope is quoted as a change request before we do it.
Do GDPR and cookie topics really come up in most projects?
Often. Cookie consent, legal pages or embedded third-party content came up in 35% of our WordPress projects and 62% of our Shopify projects. We set up the consent tool; the legal texts come from the client or their legal adviser.
How often do maintained websites need work?
Across our 18 maintenance retainers, clients sent a median of 4.3 requests per month, ranging from 1.2 to 14.7.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.