We regularly move client websites and mailboxes to new hosting – often to our own cloud infrastructure, sometimes between external providers. Hosting and migration requests made up 4% of our maintenance requests, and hosting, domain and DNS access came up in 28 of our 110 WordPress projects.
A migration done well is invisible. A migration done badly means lost emails, a site that is down for some visitors, or a broken shop. Here is what we learned.
Lesson 1: access is the first milestone
Before any technical work, we need access to:
- The current hosting (to copy files and databases)
- The domain registrar or DNS provider (to point the domain)
- The current email setup (to migrate mailboxes)
Clients' hosting sits with many different providers – IONOS, Strato, GoDaddy, all-inkl, Namecheap and others – each with its own control panel. Some do not offer common tools like cPanel or Plesk, so we work with their own interface. Domain transfers need an authorisation code from the current registrar.
Access collection is the most common source of delay in migrations. We start it first.
Lesson 2: email is the part that hurts
Websites can be copied and tested before the switch. Email is live: messages arrive every minute. When DNS changes, email routing changes with it. If the mail records are wrong or mailboxes are not ready at the new host, messages bounce or disappear.
What we do:
- Inventory all mailboxes, aliases and forwarders before the move
- Create them at the new host in advance
- Copy existing mail to the new mailboxes
- Change mail records at a quiet time
- Sync once more after the switch to catch messages delivered to the old server during propagation
- Test sending and receiving from every mailbox
If email should stay with the current provider, we make sure the website move does not touch the mail records.
Lesson 3: storage needs planning
Mailboxes and media libraries are often much larger than expected. Before a migration we check the storage needed and plan for growth. In one incident on a mail server, storage failed to mount and mailbox indexes were corrupted; recovery took careful work. Since then, storage planning and monitoring are a standard part of our migrations.
Lesson 4: DNS takes time
DNS changes are not instant everywhere. For a period, some visitors reach the old server and some the new. We lower the DNS record lifetime in advance where possible, keep the old hosting active until propagation is complete, and avoid changing content during the switch.
Moving DNS management to a provider like Cloudflare can make future changes faster and adds a layer of protection – but it is itself a change to plan carefully.
Lesson 5: test on the new server before switching
We test the site on the new server via a temporary address or local host override before changing DNS: pages, forms, shop checkout, logins, integrations. Only when everything works do we switch.
Lesson 6: check what depends on the old server
- Cron jobs and scheduled tasks
- Integrations that whitelist the old server's IP address
- SMTP settings in the website
- SSL certificates
- Hard-coded paths
Our migration checklist
| Phase | Tasks |
|---|---|
| Preparation | Collect access; inventory website, mailboxes, DNS records; plan storage; lower DNS lifetime |
| Copy | Files, databases, mailboxes to the new host |
| Test | Site on new server via temporary access; forms, checkout, logins, integrations |
| Switch | Update DNS or nameservers at a quiet time |
| Verify | Site, SSL, email send and receive, forms, integrations |
| Final sync | Mail delivered to old server during propagation |
| Clean up | Keep old hosting for a safety period, then cancel |
Migration as part of a new website
Many migrations happen together with a website launch: the new site is built on our staging environment, and at go-live it moves to new hosting at the same time. That is efficient, but it combines two risky changes. We keep them in separate steps where possible – first confirm the new hosting works with email untouched, then launch the new site – so if something goes wrong, it is clear which change caused it. On launch day, the go-live itself is usually short; the preparation around access and DNS is what takes time.
When to migrate
Good reasons to move: slow hosting, frequent downtime, poor support, outdated server software, consolidating services, or storage limits. Bad timing: during a campaign, a sale or a product launch.
FAQ
Will my website be offline during the migration?
Usually not. We prepare everything on the new server and switch DNS, so visitors move over gradually without downtime.
Will I lose emails?
Not with proper planning: mailboxes are prepared in advance, and a final sync catches anything delivered during the switch.
How long does a migration take?
The technical work is often short. The overall timeline depends mostly on how quickly access is available and on DNS propagation.
Why does hosting and DNS access matter so much?
Because the finished site cannot go live without it. Hosting, domain or DNS topics came up in 25% of our WordPress projects. Sorting out who controls the domain before the go-live week avoids a finished site waiting on staging.
How often do maintained websites need work?
Across our 18 maintenance retainers, clients sent a median of 4.3 requests per month, ranging from 1.2 to 14.7.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.
Planning a maintenance and hosting project?
If you want a realistic plan for your own project, book a short call with our team and we will walk you through the phases, what we need from you and where projects like yours usually lose time. You can also browse finished work in our maintenance and hosting portfolio.