Many website requests are not new builds: a new service page, an updated team section, a refreshed homepage banner, a second language for a few pages. We track these as website update projects. Across 10 finished update projects, the median delivery time was 8 days, with the middle half between 6.8 and 12 days. The median work logged was 5.5, spread over 2 active working days, with a median of 1 revision round.
Compare that with a full WordPress build – a median of 31.5 days and 15.2 – and it is clear why updating an existing site is often the smarter first step.
What counts as a "small" change
| Type of request | Typical effort |
|---|---|
| Text or image replacement in existing sections | Minutes to an hour |
| New page using existing templates | A few hours |
| New section type or layout on several pages | Half a day to a day or more |
| Homepage redesign within the existing site | Similar to a small project |
| New language for existing pages | Depends heavily on the number of pages and forms |
| New feature (booking, shop, listing sync) | A project in its own right |
In our maintenance retainers, the median single request took 1.2. Content and design changes specifically had a median of 1 each.
Why small changes sometimes take longer
The request grows
In 4 of our 10 update projects we recorded scope changes. The pattern is familiar: "Can you update the services page?" becomes "…and add two new services, and a new banner, and change the menu." Each addition is reasonable. Together they turn a quick task into a small project.
The content is not ready
A new page without final text can be built with placeholders, but it cannot go live. Most of the waiting in update projects happens here.
The old site was built differently
When we update a site we did not build, we first need to understand how it was built: which theme, which page builder, which plugins, which custom code. Sometimes a "simple" change touches a global template or a component used on every page. Old or abandoned plugins can make even small updates risky, and we may recommend updates first.
Legal and brand details
Updates often include legal pages or brand refreshes. New colours or fonts affect the entire site, not only the page being changed. Legal and brand topics each came up in 3 of the update projects.
How to brief a website update
A good update brief takes ten minutes and saves days:
- [ ] Which pages are affected (with links)
- [ ] What exactly should change on each page
- [ ] Final texts and images attached
- [ ] Screenshots with markings for layout changes
- [ ] Whether the change should appear in the menu
- [ ] Deadline, if there is one (for example a campaign start)
- [ ] Who approves
Update or rebuild?
A question we get often: is it worth updating the old site, or should we build a new one?
Update when the site is technically healthy (current WordPress, maintained plugins, responsive), the design still fits the brand, and the changes are about content or a few sections.
Rebuild when the site is slow, not mobile-friendly, built on an outdated or abandoned theme, or when the structure no longer matches the business. In those cases, updates become patchwork, and a redesign is more efficient. Our WordPress redesigns had a median delivery time of 36 days.
How updates are delivered
For small changes on live sites we work in one of two ways:
- Directly on the live site for low-risk text and image changes, with a backup beforehand.
- On a staging copy for layout changes, new sections, plugin changes or anything that could break the site. The client reviews on staging, and the change is then moved live.
For most update projects the client reviews once, approves, and the change goes live the same or next day.
Batch your changes
If you have several small changes, send them together in one list rather than one email per change. It is faster for both sides, easier to review, and reduces the risk of one change undoing another.
Updates within a maintenance plan
Clients with a maintenance plan send updates as part of their monthly hours. Across our retainers, clients sent a median of 4.3 requests per month. For businesses that change their website regularly – new offers, events, campaigns – this is usually more efficient than ordering each update separately.
FAQ
Can I make small changes myself?
Yes. We record short tutorials so clients can edit texts and images. For layout changes, global templates or new features, it is safer to ask us.
How fast can you change a phone number or opening hours?
Usually the same or the next working day, especially for clients on a maintenance plan.
Do you update websites built by other agencies?
Yes. We start with a short technical check so we know how the site is built before making changes.
How long does a typical maintenance request take?
The median was 1.2 hours per request across 209 requests. Integration and sync issues took longer, around 2.3 hours each.
What do maintenance requests usually involve?
Bug fixes were 21% of requests, marketing assets 16%, content and design changes 13%, and integrations 11%.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.
Planning a maintenance and hosting project?
If you want a realistic plan for your own project, book a short call with our team and we will walk you through the phases, what we need from you and where projects like yours usually lose time. You can also browse finished work in our maintenance and hosting portfolio.