The first draft is the moment clients see their website for the first time – not a static image, but a working site on our staging environment that they can click through on their laptop and phone. In our WordPress projects, it arrived after a median of 8 days from kickoff; for half of the projects it took between 5.5 and 11 days. For landing pages the median was 5 days, and for Shopify stores 9 days.
Here is what happens in that time, and why some drafts arrive sooner than others.
We build drafts, not mockups
Many agencies start with static designs in a design tool, get them approved, and only then build the site. We usually skip that step for WordPress and landing pages. Our designers build directly in WordPress with Elementor on a staging copy. The client reviews a real, responsive site with working navigation.
The advantages:
- Clients see how the site behaves on mobile from the first round
- There is no second "translation" from design to build, where details get lost
- Feedback is about the real thing, which makes it more concrete
- The approved draft is already most of the finished site
The trade-off: large structural changes after the first draft cost more than they would at mockup stage. That is why the kickoff matters.
Day by day: from kickoff to first draft
Days 1–2: kickoff and structure
We go through the brief with the client: goals, audience, pages, features, references, brand assets. We agree on a sitemap and note what content exists and what is missing. Access to the domain and hosting is requested now, even though we will not need it until launch.
Days 2–3: setup
A staging environment is created with our base theme, page builder and standard plugins. Brand colours and fonts are set globally, so every element follows them from the start.
Days 3–7: design and build
The homepage comes first, because it sets the visual direction. The other pages follow using the same components. Where content is missing, we use clearly marked placeholders – for example, a testimonial block "until the client sends their own", or a stock image to be replaced.
Before handover: internal quality check
Before a draft goes to the client, it is checked against an internal list: brand colours and fonts, prominent calls to action, mobile view of every section, broken links, forms.
What makes a draft faster
| Faster | Slower |
|---|---|
| Logo in vector format and brand colours with exact values | Logo only as a screenshot, colours "like the business card" |
| Texts delivered per page | Texts promised "later" |
| Own photos, or agreement to use stock | Photos being taken during the project |
| Clear list of pages | Pages added during the build |
| One or two reference sites with notes | Many references with conflicting styles |
Redesigns tend to be slightly quicker to the first draft than new builds: 7 days versus 8 in our WordPress data. The existing site already provides structure and much of the content.
Why the first draft is not the finished site
We intentionally show the first draft before every detail is perfect. The goal is to confirm the direction early: layout, style, structure. Polishing a direction the client does not like would waste everyone's time.
What we expect from the first review:
- Is the overall look right?
- Is the structure complete – are pages or sections missing?
- Is anything factually wrong?
- How does it look on your phone?
Detailed wording and image choices can follow in the next round.
What happens after the draft
After the first draft, the project moves into revision rounds. In our WordPress projects, that phase took a median of 21 days – considerably longer than the draft itself. Most of that time is spent waiting for feedback, not building. The go-live task afterwards took a median of 1 day.
This is why we always say: the draft is the fast part. The speed of the rest depends on how quickly feedback comes back and how consolidated it is.
When the first draft takes longer
Some drafts took several weeks. The reasons we saw most:
- The client's content arrived in pieces, so the draft was rebuilt several times
- Integrations such as booking, listings or payments needed technical setup first
- Multiple languages had to be set up from the start
- The project was paused on the client's side before the draft was finished
FAQ
Can I see a design before you build?
For most websites we show a working draft instead, because it is more realistic and faster. For custom projects we can start with wireframes or mockups.
What if I do not like the first draft?
Tell us what does not feel right, as specifically as possible. Direction changes after the first draft are part of the process; that is why we show it early.
Can you start without my texts?
Yes, with placeholders or with texts we draft for you. But final texts before the first review make the draft much more useful.
Why does one decision maker matter so much?
Because feedback from several people without a final say turns into extra revision rounds. In our experience a single person who collects feedback and approves is the biggest time-saver on the client side.
What do maintenance requests usually involve?
Bug fixes were 21% of requests, marketing assets 16%, content and design changes 13%, and integrations 11%.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.