Some of our WordPress projects went from kickoff to delivery in under two weeks. Others took months. Same team, same tools, same process. So what made the difference?
We split our WordPress projects into quartiles by duration and compared the fastest quarter (30 projects) with the slowest (28 projects).
The comparison
| Fastest quarter | Slowest quarter | |
|---|---|---|
| Median duration | 11 days | 134.5 days |
| Median revision rounds | 0.5 | 3.5 |
| Median days waiting on the client | 1.5 | 81 |
| Median days of team work in the chain | 8 | 26 |
| Median hours logged | 8.1 | 16.4 |
| Projects with missing or late content | 7% | 29% |
| Projects with scope changes | 7% | 25% |
| Projects with a reference site in the brief | 63% | 64% |
| Projects with a written content document | 77% | 82% |
What made the difference
1. Waiting time, by far
The single biggest gap is client waiting time: a median of 1.5 days in the fast group versus 81 in the slow group. The team also spent more working days on slow projects, but the gap in waiting time is many times larger.
Waiting is not only slow feedback. It includes pauses for content, logins, decisions and internal approvals on the client side – and projects that were put on hold for weeks during busy seasons.
2. Fewer revision rounds
Fast projects had a median of 0.5 revision rounds; slow ones 3.5. Every round adds implementation work and, more importantly, another wait for feedback.
3. Content ready at the start
Missing or late content appeared in 7% of the fastest projects and 29% of the slowest. Placeholders can get a draft started, but they cannot get a site launched.
4. Stable scope
Scope changes – new pages, features or sections added during the project – were recorded in 7% of fast projects and 25% of slow ones.
What did not make a difference
Reference websites
Nearly the same share of fast and slow projects had a reference site in the brief. A reference helps with style, but it does not speed a project up on its own.
Having a content document
Most projects in both groups had some kind of written content document. What matters is whether it is complete and final, not whether it exists.
What fast projects look like in practice
Reading through the fast projects, a typical pattern emerges:
- A short kickoff with the person who makes decisions
- Logo, colours, texts and photos delivered in the first days
- A clear list of pages and no new features added later
- The draft reviewed within a few days, feedback in one document
- A second round for details, then launch
Nothing exceptional – just preparation and quick decisions.
What slow projects look like in practice
The slow projects are rarely slow because of one big problem. It is usually an accumulation:
- Texts promised "next week" for several weeks
- Feedback from several people arriving separately
- New pages or a second language requested after the draft
- Long pauses during holidays or busy periods
- Access to hosting or the domain found only at launch time
Each on its own costs a few days. Together they add months.
A note on how we measured
Duration here means the time from project start to the moment the site was delivered or went live, based on the dates in our project system. Client waiting time is the time between our handing over a draft or a question and the client's next response. Revision rounds are counted from the separate feedback tasks we create for each round. Hours come from our team's timesheets. Projects without enough dated tasks were left out of each comparison, which is why the group sizes differ slightly.
The picture is consistent across other project types too. For landing pages, the fastest quarter took 7 days with 1 day of client waiting, while the slowest took 33 days with 22 days of waiting.
What this means for you
If you want your website fast, the most effective things are in your hands:
- [ ] Prepare content before kickoff
- [ ] Name one decision maker
- [ ] Block time in your calendar for reviews
- [ ] Consolidate feedback into one document per round
- [ ] Park new ideas for after launch
What we changed on our side
These findings also changed how we run projects. We ask for content and access earlier, we send clear review deadlines with each draft, and we follow up when a project has been waiting for more than a few days. When we see scope growing, we suggest a phase two instead of expanding the current project.
FAQ
Can you guarantee a delivery date?
We can commit to our part: a first draft within an agreed time and fast turnarounds on feedback. The overall date depends on content and feedback from your side.
Does paying more make a project faster?
Not really. Our data shows the timeline is driven more by waiting time and revisions than by the amount of work.
What if my content is not ready?
We can start with placeholders or draft texts for you, but launch will depend on final content.
How often do outages or security issues happen?
Less often than people fear: outages and security issues were 5% of maintenance requests, with a median of 1.4 hours to resolve. Regular updates and backups keep it that way.
Do you keep backups of maintained sites?
Yes. Backups run before updates and on a schedule, stored separately from the hosting account, so a failed update can be rolled back.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.
Planning a website project?
If you want a realistic plan for your own project, book a short call with our team and we will walk you through the phases, what we need from you and where projects like yours usually lose time. You can also browse finished work in our website portfolio.