Clients usually ask "how long will it take?" and mean calendar weeks. But there is a second, equally useful question: how much actual work goes into a website? We looked at the hours our team logged in our timesheets across finished projects.
The short answer: a lot less than the calendar suggests. Our WordPress projects logged a median of 15.2 of work, spread over a median of 7 working days on which someone actually worked on the project. Yet the median project took 4.5 from start to delivery. The difference is mostly waiting – for content, feedback and decisions.
Hours by project type
| Project type | Projects | Median hours | Typical range (middle half) | Median active days |
|---|---|---|---|---|
| WordPress website | 110 | 15.2 | 9.3 – 32.1 | 7 |
| Landing page | 45 | 9.4 | 5.2 – 14.5 | 5 |
| Shopify store | 8 | 29.4 | 22.7 – 49.8 | 10 |
| Website update or new pages | 9 | 5.5 | 2.1 – 6.8 | 2 |
| One-time SEO setup | 23 | 4.7 | 3.8 – 8.7 | 3 |
These numbers reflect our way of working: WordPress with Elementor, a proven set of plugins, internal templates and a team that builds websites every week. An agency starting from scratch for every site would log more.
What pushes the hours up
The median hides a wide spread. Some WordPress projects needed under 9.3; a quarter needed more than 32.1. When we split the projects by features and circumstances, clear patterns appeared:
| WordPress projects with… | Median hours |
|---|---|
| Missing or late content | 32.6 |
| Content ready on time | 13.5 |
| Multiple languages | 32.5 |
| One language | 13.5 |
| Booking features | 30.1 |
| Payments or a shop | 27.7 |
| 0–1 revision rounds | 9.2 |
| 4 or more revision rounds | 32.4 |
Three things stand out.
Revisions drive hours more than anything else
Projects with four or more revision rounds needed more than three times the hours of projects with none or one. Every round means reading feedback, clarifying, changing, checking mobile, and preparing the next version.
Missing content costs work, not only time
You might think waiting for content only costs calendar time. It also costs hours: placeholder texts and images get built, then replaced, then adjusted when the real content is longer or shorter than expected. Projects with missing content logged more than twice the hours of those with content ready.
Languages and processes add real work
A second language is not just translation. Every page, menu, form, email and SEO field exists twice and must be checked twice. Booking and payment features add configuration and testing.
What the hours are spent on
A typical WordPress build in our timesheets breaks down into these activities:
- Setup and structure – staging environment, theme, plugins, sitemap.
- First draft – design and building of all agreed pages with the content available.
- Revision rounds – implementing feedback, one task per round.
- Quality check – mobile view, forms, links, speed, brand colours, legal pages.
- Go-live – moving the site to the live domain, DNS, SSL, final checks.
The first draft is usually the largest single block. Revision rounds come second – and they are the part the client influences most.
Why hours and calendar time differ
In our WordPress projects, the team worked on the project for a median of 16.5 days of the chain between first draft and launch, while the client side took a median of 13.5 days. Across all builds, 61% of the elapsed time from draft to go-live was spent waiting on the client.
That is not a criticism of clients – business owners have other priorities. But it explains why a project with around fifteen hours of work can take more than a month in the calendar, and why preparation shortens both.
How to keep the hours down
- Deliver texts, images and logins before the first draft
- Send feedback as one consolidated document per round
- Decide on languages and features before the build, not during revisions
- Nominate one person to approve
Hours are also a planning tool for you
Knowing the effort helps you plan your own side. For every hour our team spends, there is client time too: writing or approving texts, choosing photos, reviewing drafts, collecting feedback from colleagues and testing forms. Blocking two or three short slots in your calendar during the project – one for each review round – is often the single best thing you can do to keep a website on schedule.
FAQ
Why do you not quote by the hour?
For website builds we work with defined packages and scopes, which gives clients price certainty. The hours in this article are what our team actually logged, not what clients were billed.
Is a website with fewer hours a worse website?
No. Low hours usually mean a clear brief, ready content and few revisions – not less quality.
How many hours does a multilingual website need?
In our data, multilingual WordPress sites needed a median of 32.5, compared with 13.5 for single-language sites.
Do you build websites from templates?
We start from our own tested layouts and components, then adapt them to your brand and content. That is one reason first drafts come quickly; the design is still specific to your business.
How often do maintained websites need work?
Across our 18 maintenance retainers, clients sent a median of 4.3 requests per month, ranging from 1.2 to 14.7.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.