Clients ask us every week how long a project will take. For years we answered from experience. This year we went through our project system properly: 233 finished projects, 909 tasks, 2908 timesheet entries and the conversations attached to them. This article summarises what we found. Individual articles on our blog go deeper into each project type.
A note on method: all numbers are medians (the middle project), with the middle half of projects as a range where useful. We removed client names and private details; nothing here identifies a client.
The overview
| Project type | Finished projects | Median delivery time | Median hours logged |
|---|---|---|---|
| WordPress website | 110 | 31.5 days | 15.2 |
| Landing page | 45 | 14.5 days | 9.4 |
| One-time SEO setup | 24 | 6 days | 4.7 |
| Website update | 10 | 8 days | 5.5 |
| Shopify store | 8 | 44 days | 29.4 |
Other project types – custom software, headless websites, CRM setups, automations, design work and email marketing – had too few finished projects in the period for reliable statistics. We describe them from experience in separate articles.
Finding 1: most of the calendar is waiting
Across our website and landing page builds, 61% of the time from first draft to go-live was spent waiting on the client – for feedback, content, access or decisions. The actual work is much shorter than the calendar suggests: a WordPress site needed a median of 7 active working days.
This is not a complaint. Business owners have businesses to run. But it explains why preparation matters more than any other factor.
Finding 2: revision rounds are the biggest lever
Builds with no revision round were delivered in a median of 8.5 days. With two rounds, 22 days. With three, 64 days. The jump after the second round is where projects lose their momentum.
Finding 3: content is the most common blocker
WordPress projects with missing or late content took a median of 74 days, compared with 26 days when content was ready.
Finding 4: features add time predictably
| WordPress projects with… | Median delivery time |
|---|---|
| One language | 26.5 days |
| Multiple languages | 79 days |
| Payments or shop features | 42 days |
| Booking features | 56 days |
Each of these adds decisions, configuration and testing – and more things for the client to confirm.
Finding 5: the same problems come up again and again
The most frequent topics in WordPress feedback and support were brand details like fonts and colours (52% of projects), mobile layout (38%), legal and cookie questions (35%), hosting and domain access (25%) and missing content (21%). None of them are exotic. All of them can be prepared for.
Finding 6: SEO setups are quick when access is ready
One-time SEO setups took a median of 6 days and 4.7. 16 of 24 needed no revision round at all. The main dependency is access to the website and Google accounts.
Finding 7: launch is not the end
34% of WordPress clients came back with new requests after launch, the first after a median of 12 days. In our maintenance retainers, a typical client sent 4.3 requests per month, each taking a median of 1.2.
Finding 8: fast projects are not fast because of luck
We compared the fastest and slowest quarter of our WordPress projects. The fastest took a median of 11 days, the slowest 134.5. The fast group waited on the client for a median of 1.5 days and needed 0.5 revision rounds; the slow group waited 81 days and needed 3.5 rounds. Having a reference website made no difference – almost the same share of both groups had one. Ready content, one decision maker and consolidated feedback did.
What we changed because of this
- We ask for content, logins and brand assets before kickoff, not during the build
- Each draft goes out with a clear review deadline
- We encourage one consolidated feedback document per round
- New ideas during a project are collected for a phase two
- Launch checklists now include forms, tracking, legal pages and email tests
How to use these numbers
Use them as a realistic baseline, not a promise. A small single-language site with ready content and one decision maker can be much faster than the median. A multilingual site with booking and content still being written will take longer. Our team will give you a specific estimate for your project.
FAQ
Are these numbers typical for all agencies?
They reflect our way of working: WordPress with Elementor, Shopify, internal templates and a dedicated team. Other agencies and approaches will differ.
Why use medians instead of averages?
A few very long projects – for example ones paused for months – would distort an average. The median shows what a typical project looks like.
Which article should I read next?
Start with the article for your project type: WordPress timelines, Shopify, landing pages or SEO. Each one breaks the timeline down by phase.
What delays website projects the most?
Waiting. Across our website and shop builds, 61% of the time between the first draft and go-live was spent waiting on the client – for content, feedback, approvals or access – not on design or development.
What do the fastest website projects do differently?
Our fastest quarter of WordPress projects took a median of 11 days, the slowest 134.5 days. The team work differed far less than the waiting: 1.5 versus 81 days spent waiting on the client.
Where the numbers come from: our own project records in Odoo – 233 finished projects, 909 tasks and about 4941 logged hours, mostly from 2025–2026. Durations are calendar days from kickoff and we quote medians, so one unusually long project does not distort the picture.